Beecholme Primary School

Posted by

Project Details

Type                           Flat Roofing

Duration                   9 weeks

Manufacturer         Garland

Scope:

Erect access scaffold, working platforms and edge protection. Main flat roof area – removal of the existing canopies to five separate locations and the installation of new Xtralight canopies. Roof Areas 3, 4 and 5 – repair and preparation of the existing roof coverings and the installation of a new Garland overlay system comprising vapour barrier, insulation, underlayer and cap sheet. Ancillary works included new fascias, new door and frame to boiler house. The installation of guardrails to the boiler house access and around the new canopies. Due to the location of the canopies, the majority of these works were completed during the six week school summer holiday period.